Shanghai Petrochemical Ministry of Chemical Industry No. 2 glycol plant feeds

In the morning of March 3, 2007, the No. 2 ethylene oxide/ethylene glycol unit of Shanghai Petrochemical's Chemical Ministry was running normally, and qualified products were produced on the 5th.

On the morning of the 3rd, under the unified command of the General Command of the General Motors, the operating procedures for feeding and driving were being carried out in an orderly manner. At 10.30 a.m., the driving conditions were reconfirmed and the production plant was immediately introduced with ethylene raw materials. At 2 o'clock in the afternoon, oxygen was successfully introduced into the system, marking the success of the glycol plant. The raw material passed a long reaction process in the ethylene glycol device system. At 21:00 on the 4th, the ethylene glycol device produced qualified products.

The No. 2 ethylene glycol plant is one of the main projects for the construction of Shanghai Petrochemical's structural adjustment project and is also the main growth point of Shanghai Petrochemical's economic benefits this year. After the plant is put into operation, it will add 380,000 tons of ethylene glycol per year, plus the capacity of No. 1 glycol plant of 225,000 tons. The annual production capacity of ethylene glycol of Shanghai Petrochemical will reach 600,000 tons or more, and it will become an area in East China. One of the important production bases for fat raw materials will meet the domestic raw material supply demand for polyester products, provide more ethylene glycol (EG) and ethylene oxide (EO) products for the domestic market, and can further strengthen Shanghai Petrochemical's olefins - The core business of polyolefin chain, increase chemical production capacity and production varieties, and enhance the integrated economic benefits of oil refining and chemical industry.

The construction project of No. 2 ethylene glycol plant was reviewed by the expert group of Sinopec Group Company in May 2005. Piling began on January 25, 2005 and was completed on December 20, 2006. After that, the Ministry of Chemical Industry of Shanghai Petrochemical spent nearly two months to concentrate its efforts on preparing the device for driving.

During the construction period of the No. 2 ethylene glycol plant, which is the main construction project of Shanghai Petrochemical's structural adjustment project, the Shanghai Petrochemical Engineering Quality Supervision Station has always put the project quality first and established “doing a good job in quality supervision. "Service for the field" concept. In order to control the quality of the project, Shanghai Petrochemical Engineering Quality Supervision Station went deep into the construction site as soon as it started, timely convened a project quality meeting, communicated project construction quality control requirements, construction technical measures, etc. with all parties involved in construction and actively participated in the project. The discussion of the construction plan and the problems encountered during the construction process discussed the consultation, solved many practical problems in construction, and achieved good results.

In order to ensure project quality, strengthen construction site management, and promote communication and coordination with construction units, supervision units, and construction units, Shanghai Petrochemical Engineering Quality Supervision personnel often in-depth construction site, in order to not affect the normal construction progress, some comrades often Give up the rest time, go to the construction site to carry out the project quality supervision and inspection, in the usual project quality supervision and inspection, increase the frequency and intensity of spot checks, and timely master the construction of the first-hand information. In order to ensure that the No. 2 ethylene glycol plant project can be delivered on time, the Shanghai Petrochemical Engineering Quality Supervision Station carried out several quality inspections and special project quality inspections. The quality issues that were checked out were promptly met by the supervision and construction units. The rectification of the purlins was carried out, and the quality supervision station conducted a quality visit, eliminated some hidden dangers in the project quality, and eliminated the project quality problems in the construction phase. It has created the conditions for the timely completion of the construction of the No. 2 glycol plant project, and also provided a useful exploration for how Shanghai Petrochemical’s engineering construction works in the supervision of project quality and accumulated some experience.

In order to ensure the quality of the ethylene glycol plant project is completed, the Shanghai Petrochemical Engineering Quality Supervision Station assigns full-time personnel to take charge of it. The relevant departments of Shanghai Petrochemical have established a project department based on the characteristics of the project, and are responsible for project construction management. With the joint efforts of various participating units, the project construction has achieved the requirements of “safety, quality, efficiency, and economy”. Sinopec's quality inspection team also conducted inspections on the project's quality behavior, physical quality, and construction materials. The overall status is good.